Seasonal Timing

The same phase takes longer in winter. Tell OperoNMS once, and every plan knows.

What it is

A table with one row per phase and one column per month. In each box you type extra days (+) or fewer days (−) for a phase that starts in that month. Empty or 0 means no change. The unit follows “Durations entered in” (days or weeks).

The Seasonal Timing tab (empty, on a draft)
The Seasonal Timing tab (empty, on a draft)
  1. 1The hint: extra (+) or fewer (−) days for each phase, depending on the month the phase starts.
  2. 2Base: the normal duration from the Phases tab.
  3. 3Jan to Dec: the month the phase starts in.
  4. 4Type a number into a box. Negative shortens the phase. It saves when you leave the box.
  5. 5Total lead time if started in: the whole recipe's length for a batch started in each month.
  6. 6Set a Range of Months… fills many boxes at once.
  7. 7Clear All Seasonal Changes empties every box, for every phase.
Set a range of months
Set a range of months
  1. 1Phase: choose the phase.
  2. 2From and To: the first and last month. A range can run over the year end, for example Nov to Feb.
  3. 3Change: days to add (negative to remove).
  4. 4Apply writes the number into every month of the range.
After filling it in
After filling it in
  1. 1The two grafting phases take +7 days when they start May to August.
  2. 2Fold bag: clonal roots form takes +14 days in May to August (set with the range form).
  3. 3The lead time now depends on the start month: 48 weeks for a January start, 50 for February to May, 47 for August to December.

What it means and how it is used

What matters

Common mistakes

Try it